Als erstes wurde die Gebäudehülle der Bestandhallen für den Anbau des Hochregal-
Parallel dazu wurden die Sozialräume für die Lagerarbeiter modernisiert.
First of all, the building shell of the existing site was prepared for the outbuilding of the high rack storage.
The next step was the reconstruction of the steel construction at the existing site.
At the same time, the social and break rooms for the storekeepers have been streamlined. After that, the base and the rack frame needed to be compiled. In order have the latest electronics, the primary power, the electronic data processing system,the internal electronic, the alarm system and the video surveillance system have been modernized. The steel frame of the high rack storage was covered with aluminum sandwich elements and a cladding of glass was added, which improves the energetic statement and shows off the modern storage logistic.
Thus, the connection between the high rack storage and the existing site was established and the sprinkler installation was assembled. While the craftsmen were busy, applying the inner conveyors and the in and out stations, the redevelopment of the floor, walls and steel hall construction was in process well. Also the waste disposal was taken care of: After the new in and out station was ready, the waste management system was built. An access yard was established to coordinate the temporary storage and the evacuation of the waste.